Budget

Thornton Residence (GC-2024-001)

Budget Status

Draft - Awaiting Review

Last import:

2024-04-20

Contract Value

$850,000

Total Budget (Ex-GST)

$573,465

Projected Profit

$276,535

32.5% margin

Preliminaries
8 items
$130,550
CategoryDescriptionQtyUnitRateAmount
Project Management
PM FeeAI Estimate
26wks$1,200$31,200
Site Supervision
Site ForemanAI Estimate
26wks$2,800$72,800
Insurance
Contract Works InsuranceAI Estimate
1allow$4,500$4,500
Licenses & Permits
QBCC LicenceAI Estimate
1allow$800$800
Licenses & Permits
Council Building PermitAI Estimate
1allow$3,200$3,200
Software & Estimating
Cost CubingAI Estimate
1allow$450$450
Site Establishment
Site Sheds & AmenitiesAI Estimate
1allow$8,500$8,500
Waste Removal
Skip BinsAI Estimate
26wks$350$9,100
Preliminaries Total$130,550
Milestone 1: Site Works & Base
5 items
$54,600

Demolition

$15,000
Strip & Clear SiteAI Estimate
1allow$15,000$15,000

Concrete

$19,500
FootingsAI Estimate
45m2$180$8,100
Ground SlabAI Estimate
120m2$95$11,400

Site Works

$20,100
Bulk ExcavationAI Estimate
1allow$12,000$12,000
Retaining WallsAI Estimate
18lm$450$8,100
Preliminaries$130,550
Trade Costs$414,015
Subtotal$544,565
Contingency (5%)$28,900
Total Budget (Ex-GST)$573,465
GST (10%)$57,347
Total Budget (Inc-GST)$630,812
Contract Value$850,000
Projected Profit$276,535
Gross Margin32.5%