Thornton Residence

GC-2024-001

Active
45 Seaside Drive, Thornton NSW 2322
1 Feb 2024 - 30 Oct 2024
Original Contract

$850,000

Approved Variations

+$12,500

1 variations

Revised Contract

$862,500

Projected Profit

$122,500

14.2% margin

Spent to Date

$267,000

Retention Held

$19,125

5% retention

Budget Remaining

$473,000

Tender Coverage
Loading...
Milestone Schedule
Track progress through contracted milestones

1/5 complete

1

Base Stage

Completed

Due: 15 Mar 2024

Contracted

$170,000

Budget

$145,000

Spent

$142,000

P&L

+$28,000

2

Frame Stage

In Progress

Due: 1 May 2024

Contracted

$212,500

Budget

$180,000

Spent

$125,000

P&L

+$87,500

3

Lock-Up Stage

Pending

Due: 1 July 2024

Contracted

$212,500

Budget

$190,000

Spent

$0

P&L

+$212,500

4

Fixing Stage

Pending

Due: 1 Sept 2024

Contracted

$170,000

Budget

$150,000

Spent

$0

P&L

+$170,000

5

Practical Completion

Pending

Due: 30 Oct 2024

Contracted

$85,000

Budget

$75,000

Spent

$0

P&L

+$85,000