VO-001

Additional structural steel for extended balcony

Approved
Variation Details

Affected Milestone

Frame Stage

Date Submitted

25 Mar 2024

Date Approved

28 Mar 2024

Description

Change Description

Additional structural steel for extended balcony

Reason for Change

client request

Cost Breakdown
Labour$5,000
Materials$6,250
Overheads & Margin$1,250
Activity Log

Variation Created

25 Mar 2024 by John Smith (PM)

Submitted to Client

25 Mar 2024 by John Smith (PM)

Approved by Client

28 Mar 2024 - Client signed off

Cost Impact
Amount (ex GST)$12,500
GST (10%)$1,250
Total (inc GST)$13,750

Contract Updated

This variation has been added to the contract value

Contract Impact
Original Contract$850,000
+ This Variation$12,500
Revised Contract$862,500