Variation Details
Affected Milestone
Frame Stage
Date Submitted
25 Mar 2024
Date Approved
28 Mar 2024
Description
Change Description
Additional structural steel for extended balcony
Reason for Change
client request
Cost Breakdown
Labour$5,000
Materials$6,250
Overheads & Margin$1,250
Activity Log
Variation Created
25 Mar 2024 by John Smith (PM)
Submitted to Client
25 Mar 2024 by John Smith (PM)
Approved by Client
28 Mar 2024 - Client signed off
Cost Impact
Amount (ex GST)$12,500
GST (10%)$1,250
Total (inc GST)$13,750
Contract Updated
This variation has been added to the contract value
Contract Impact
Original Contract$850,000
+ This Variation$12,500
Revised Contract$862,500