Harbourview Duplex
GC-2024-002
Active
12-14 Harbour Street, Newcastle NSW 2300
15 Mar 2024 - 28 Feb 2025
Original Contract
$1,450,000
Approved Variations
+$0
0 variations
Revised Contract
$1,450,000
Projected Profit
$1,200,000
82.8% margin
Spent to Date
$85,000
Retention Held
$0
5% retention
Budget Remaining
$165,000
Tender Coverage
Loading...
Milestone Schedule
Track progress through contracted milestones
0/1 complete
1
Base Stage
In ProgressDue: 15 May 2024
Contracted
$290,000
Budget
$250,000
Spent
$85,000
P&L
+$205,000